The National Gas Company of Trinidad and Tobago Limited (NGC) advises that it will commence the following activities on its TAGSS Project, located at Picton Road, Debe.

  • Flaring
  • Hot tapping
  • Commissioning of NGC’s 24-inch pipeline

Works include, but are not limited to:

  • Pigging and hydrotesting of the pipeline
  • Flaring in a controlled manner via flare stack
  • Commissioning (introduction of hydrocarbons) into the pipeline

These works will be carried out in phases. Details of the planned activities are as follows:

Scheduled Start: Friday 2nd June 2023
Scheduled End: Friday 16th June 2023

These activities are scheduled to take place between the hours of 7:00 a.m. and 7:00 p.m.