The National Gas Company of Trinidad and Tobago Limited (NGC) will commence activities for the introduction of nitrogen into its 16-inch low-pressure pipeline, located at Beetham Highway. It will also conduct flaring at City Gate Valve Station, Morvant Junction.
Works include, but will not be limited to the following:
Beetham Highway
- Excavation on the eastbound lane
- Injection of nitrogen into the pipeline
- Backfilling
City Gate Valve Station, Morvant Junction
- Flaring in a controlled manner via flare stack
Details of the planned activities are as follows:
Scheduled start: Saturday 9th December 2023
Scheduled end: Saturday 9th December 2023
Hours of Work: 7:00 a.m. to 7:00 p.m.